A federal court has ordered an immediate halt to dredging operations at Progreso’s deepwater port following a lawsuit filed by coastal communities and environmental activists. The project, which involves dredging and landfill work across more than 80 hectares (198 acres), was suspended on Thursday after the 14th Circuit Federal Tribunal granted provisional relief in Amparo Case 1919/2025.
The tribunal found that work had proceeded without the required environmental permits, including the mandatory Environmental Impact Statement from Mexico’s environment ministry. Attorneys Juan Andrés Medina Rejón and José Alfredo Uicab Panti, who filed the case on behalf of communities in Progreso, Chicxulub and Chelem, said the port authority failed to obtain proper authorization before beginning construction.
“The measure granted is a key step to protect the sea, artisanal fishing and the rights of coastal communities,” Medina Rejón said. “The dredging cannot continue without environmental guarantees or public consultation.”
The suspension order requires the National Port System Administration of Progreso to prove compliance within 24 hours. Port authorities face a hearing Friday related to the amparo proceeding.
The port expansion project represents one of Mexico’s most ambitious maritime infrastructure developments. The 7.9 billion peso ($400 million) initiative aims to deepen the navigation channel to 14 meters (46 feet), widen it to 180 meters (590 feet), and extend it to 10 kilometers (6.2 miles).
Work began in January when the Fernando de Magallanes, one of fewer than 20 advanced dredging vessels worldwide, arrived from Europe. The 138.5-meter (454-foot) ship was brought specifically to handle Progreso’s hard seabed conditions. Governor Joaquín Díaz Mena has championed the project as the cornerstone of his Maya Renaissance Plan for regional economic development.
The expanded port would increase operational capacity from 36 to 116 hectares (89 to 287 acres) and allow vessels carrying up to 100,000 tons to dock, nearly triple the current 36,000-ton limit. Officials project the modernization will transform Progreso into a major logistics hub connecting the Maya Train cargo corridor with maritime trade routes.
But plaintiffs argue the project moved forward without crucial scientific studies. Attorneys said missing documentation includes bathymetric and morphological surveys of the seabed, assessments of cumulative coastal impacts, and any public consultation with affected communities.
The tribunal determined that continuing work posed a risk of irreparable environmental damage. The court ordered all parties notified and directed them to monitor compliance with the suspension.
The case echoes a landmark 2022 Supreme Court decision that halted expansion of the Port of Veracruz over similar concerns. In that ruling, Mexico’s highest court established that fragmenting environmental reviews violates citizens’ constitutional right to a healthy environment. The Veracruz decision set a precedent requiring holistic assessment of major infrastructure projects.
Medina Rejón called on civil society, media and independent organizations to monitor compliance with the court order and demand transparency. “The right to a healthy environment is a constitutional right,” he said. “We cannot allow destruction of our marine ecosystems without studies, without information and without social responsibility.”
The tribunal will determine in coming days whether to grant a permanent suspension, which could keep work halted until the amparo case is fully resolved. Port authorities have not yet commented publicly on the ruling.
The project was launched by President Claudia Sheinbaum in an April ceremony at the port. Officials initially projected completion by the end of 2025, though the timeline assumed uninterrupted construction.
Key Facts About the Progreso Port Suspension
- Federal court granted provisional suspension of dredging Thursday in amparo case 1919/2025
- Project involves 80+ hectares (198 acres) of dredging and landfill at Progreso’s deepwater port
- Work proceeded without Environmental Impact Statement or required permits, plaintiffs say
- Communities from Progreso, Chicxulub and Chelem filed suit citing lack of public consultation
- Port authority must prove compliance within 24 hours of court notification
- Full project budget: 7.9 billion pesos (approximately $400 million)
- Planned improvements: channel depth to 14 meters (46 feet), width to 180 meters (590 feet)
- Case follows 2022 Supreme Court precedent requiring comprehensive environmental reviews
Sources: Diario de Yucatán, Courthouse News Service, Dredging Today